Victoria Parade pedestrian pavement works

Published on 02 March 2017

Pavement works on Victoria Parade, will commence on Monday 6 March as part of continued Riverbank Revitalisation road and footpath improvements.

These works will involve concrete and granite paving of pedestrian crossings in the area and is due to be completed by Tuesday 18 April 2017, weather-permitting.

During this time, the southbound lane of Victoria Parade will be temporarily closed between Royal Street and Quay Lane. One-way traffic will be directed northbound in this area. Southbound traffic will be detoured via East Street.

Pedestrian and vehicle access will be available to all businesses and residences throughout construction.